Permit Board - Fulham Solar Farm

Last Updated 2/03/2026 6:48:53 AM

Type
Employer
Location
Start
End
Status
PER-125037
Excavation and Ground Penetration Permit
GGC
Daniel Stewart
GGC Site Compound / Substation
Substation / Substation
6:45 AM
16/02/2026
5:00 PM
12/03/2026
In Progress
PER-127280
Excavation and Ground Penetration Permit
BMC - Screw Piles for BESS
Geoff Kyle
+ 2 other supervisors
Block 08 / Block 08 & 09
Block 09 / Block 08 & 09
+ 1 other zones
4:06 PM
19/02/2026
4:06 PM
18/03/2026
In Progress
PER-130612
Excavation and Ground Penetration Permit
Solidity - BMC Subcontractor
Tom McIntosh
Block 01 / Stage 1 and 2 Feeders - Blocks (1,2,8,9) (15,21,16,3,5)
Block 02 / Stage 1 and 2 Feeders - Blocks (1,2,8,9) (15,21,16,3,5)
+ 5 other zones
7:25 AM
28/02/2026
5:00 PM
27/03/2026
In Progress
Hot Works Permit - VIC Fire Danger Period / Extreme Fire Danger Rating
Lawrence Engineering
No Nominated Rep
Block 11 / Blocks 11 & 12
Block 12 / Blocks 11 & 12
7:00 AM
4:30 PM
Pending Approval
Hot Works Permit - VIC Fire Danger Period / Extreme Fire Danger Rating
GGC
Daniel Stewart
Substation / Within fenced area of Sub-Station Pad
7:15 AM
4:45 PM
Pending Approval
Excavation and Ground Penetration Permit
Solar Farm Constructions
Michael Kelly
Whole Site / Fulham Solar Farm
7:01 AM
1:00 PM
4/04/2026
Pending Approval
Excavation and Ground Penetration Permit
Solar Farm Constructions
Michael Kelly
Whole Site / Fulham Solar Farm
3:30 PM
6/02/2026
5:30 PM
1/03/2026
Expired 13 hours ago
Not Stopped